NOTICE TO NAVIGATION INTERESTS
ST. LOUIS DISTRICT DATE: 11/30/2022 NOTICE NUMBER: 201663
ATTN: CEMVS-DE
1222 SPRUCE STREET
ST. LOUIS MO 63103-2833
HTTP://WWW.MVS.USACE.ARMY.MIL/
POC:
Lance Engle LOCAL NUMBER:
WATERWAY: UPPER MISSISSIPPI
EFFECTIVE: 11/30/2022 12:00 thru UNTIL FURTHER NOTICE
________________________________________________________________________________________________________________________

Channel Maintenance Update 30 November 2022
Dredge Hurley, Mile 103-102 UMR
Upper Mississippi River

 

  1.  The Dredge Hurley will arrive at mile 102.5 UMR on the afternoon of 30 November 2022 to begin dredging operation from mile 103 to 102 UMR.  Work at this location estimated to take 9 days and complete on 9 December 2022.  Updates to the Dredge Hurley's schedule will be provided as work progresses.

  2. The Dredge Hurley and its attendant plant, to include tender boats, small boats, barges and pipeline, etc., work 24 hours a day, 7 days a week. When dredging, removed river bottom material is pumped through a pontoon pipeline, which may be crossing the channel, and is placed outside of the navigation channel. Mariners should be on the lookout for tender boats, barges, small survey boats, and pipeline when transiting the dredge area.

  3. The Dredge Hurley may be contacted on Marine VHF-FM radio channels 13 and 16. Mariners are urged to transit at their slowest safe speed to minimize wake and proceed with caution after passing arrangements have been made with the Dredge Hurley.

FOR THE DISTRICT ENGINEER:

 

//signed//


Andrew C. Schimpf, P.E.